The Lake Jualbup Accord project has now come to a close. The final report has been submitted to the City of Subiaco, and provides an overview of the findings of the six focus areas of the project and the associated options. The report was informed by four key pieces of work, including:

  • RPS’s technical review on water options
  • order of magnitude costings by Syrinx Environmental
  • a community survey
  • Aboriginal heritage consultations.

The above reports, apart from the Aboriginal Heritage report, are available on the City of Subiaco website and project websites. The Aboriginal Heritage report is confidential due to provisions named in Section 7(1)(b) of the Aboriginal Heritage Act.

The City of Subiaco is preparing to submit a report to its February Corporate, Community and Technical Services (CCaTS) Committee meeting to be held on Tuesday 21 February.

The final project report from Aha! Consulting will be available on the city’s website as part of the CCaTS agenda on Tuesday 14 February. For more information, or to submit a question in relation to the project, see the city's website.

 

Community Reference Group

The Lake Jualbup Accord Community Reference Group (CRG) has now been disbanded. The CRG have made a real and valuable contribution to the project. They were involved in helping shape the survey process and questions, and played a key role in ensuring the process remained accountable to the community. A huge thanks and acknowledgement to all the CRG participants for their work and time invested.

On behalf of Aha! Consulting, I would like to thank you for your interest, commitment and contribution to this project.

The following links reload the page with different content below.

Email UsLake Jualbup News

Community Survey Extended

There have been some delays from Australia Post in the delivery of postcard to some houses/residents. However, we are informed that all properties should have now received theirs.

Due to the delay the survey has been extended until 5pm Wednesday 23 November.

Surveys can be completed online at www.savant.net.au/lakejualbup.

  • In order to complete the survey, you will need to enter the individual five letter password printed on the Lake Jualbup postcard.
  • Paper copies can be access through contacting the City of Subiaco phone: 9237 9222 or email: city@subiaco.wa.gov.au

A notice will also be placed in the 19th of Novemebr edition of the Post newspaper.

 

Have your say about the RPS desktop review.

Have your say about the RPS desktop review.

Technical consultants RPS Group were engaged to complete a desktop review of past studies (comissioned and community) and options for water retention in the Lake.

The Consultants were asked to:

  • Review the findings of the research by Dr Geoffrey Dean to determine the impact of these findings on the options available
  • Review the feasibility of the options presented in previous reports (without 'Re-inventing' the work that has occurred prior)
  • Investigate the feasibility of emerging and/or additional methodologies being suggested (ie: use of semi-permeable membranes)
  • Confirm the cost estimate for the implementation and maintenance of these options

The updated report (4MB) is now available. 

If you have any comments on this report, please go to the discussion forum on this site

Community Survey Closed

The Community survey is now closed. SAVANT strategies and systems are working on the report and the results will be made available as part of the final report being presented to Council.

Community Survey Open

Community Survey Open

Between the 7th of November and 9:00am Monday 21st of November members of the subiaco community have an opportunity to provide feedabck on their preferences for the future of Lake Jualbup.

A postcard with a unique code is being mailed to all residences and businesses to acces an online survey Nb: The code allows for one resposne per-household/business.

To access the online survey make sure you have your code and then follow this link

www.savant.net.au/lakejualbup

If you want to access a paper based version, then you can pick one up from the City of Subiaco Administration building or make contact with them. You will

read more

Reference Group Minutes 25th Oct 2011

The community reference group held a meeting on the 25th October to conitnue dicussions on the community survey . Click here to view the minutes

Reference Group Minutes 17th Oct 2011

The community reference group held a meeting on the 17th October to conitnue  dicussions on the community survey process. Click here to view the minutes

 

Reference Group Minutes 29th Sept 2011

The community reference group held a meeting on the 29th September to commence dicussions on the community survey process. Click here for the minutes

Reference Group Minutes 19th Sept 2011

The community reference group held an additimopal meeting on the 19th
September to commence dicussions on the community survey process. Click here for the minutes

Reference Group Minutes and Ammended Terms of Reference

The Community Reference Group met on the 5th Sept 2011. The meeting minutes and ammended terms of reference are now available.

Reference Group Announced

Drawn from 17 submissions, nine community members have been selected to form the Lake Jualbup reference group:

  • Mr Daniel Boase-Jelinek
  • Dr Timothy Dean
  • Ms Bianca Della Vedova
  • Ms Roz Hart
  • Dr Anne Karczub
  • Mr Frank Marshall
  • Ms Daniela Simon
  • Mr Mark Wilshusen
  • Mr Ray White

Positions were filled through a public expression of interest process, and the project team expresses its sincere thanks to those who made submissions. For the full outline of the selection process please click here.

Two members of the previously formed 'integrity team' will be part of the reference group, Mr Chris Mabbott JP and Mrs Lana Noack. Mr Mabbott is a former police officer and current justice of the peace, Mrs Noack is a fellow of Leadership WA and neither are residents of Subiaco and both are volunteering their time to this project.

Purpose

The reference group's role is to provide feedback to the Lake Jualbup project team on matters such as:

  • proposed community survey
  • implications of survey outcomes
  • community engagement process as the project develops
  • selection of management plan design consultants
  • informing the community on the project's progress and outcomes.

In performing its role, the reference group will have access to appointed technical consultants RPS.

7e43839cf7e189c209484e9109b34a8738e49319